Metro-area highway system upgrades continue

Published: Friday, March 19, 2021 By: Chamber Staff Source: The POINT!
to resurface I-40 for $1.4 million between the I-35/Fort Smith Junction and Sooner Road to prep the driving surface for the upcoming project. Work will be completed by early May 2021.

I-40

I-40 and Sooner Road

I-40 EAST CORRIDOR STUDY FROM I-35 TO DOUGLAS BOULEVARD

This ongoing engineering study is looking at traffic patterns, future traffic growth and other future needs of the I-40 corridor such as additional lanes, modification to access such as ramps and frontage roads and new bridges.

The $1.6 million study contract was awarded in 2015 and is in progress. The corridor study is broken into two areas: I-40 between Reno Avenue and Hudiburg Drive, and I-40 between Hudiburg Drive and Industrial Boulevard.

I-40 INTERCHANGE CONSTRUCTION AT FRISCO ROAD IN YUKON

A new I-40 interchange will be built at Frisco Road in Yukon to relieve traffic congestion at nearby interchanges including Garth Brooks Boulevard.

This $14 million project was awarded in July 2020 and work began in September 2020. Completion is expected to take nearly a year. The project is in partnership with the City of Yukon and the Federal Highway Administration.

I-35

I-35 BRIDGE REHABILITATION OVER STILLWATER CENTRAL RAILROAD BETWEEN JUST SOUTH OF I-40 AND THE OKLAHOMA RIVER AND SE 15TH STREET

The I-35 bridge between Southeast 15th Street and I-40 and the Oklahoma River will be rehabilitated and will include deck and limited structure repairs.

The contract of just less than $2 million was awarded and work was expected to begin March 1, 2021, and continue through summer 2021.This work will be very disruptive to traffic as the bridges will be worked on one-half at a time. This means traffic will be narrowed to two lanes in each direction and the project will include intermittent ramp closures.

I-35 CORRIDOR STUDY IN MOORE AND NORMAN

ODOT, City of Moore and City of Norman partnered on a $775,000 study beginning in 2017 to look at I-35 interchanges, on- and off-ramps and service roads between just north of North 5th Street in Moore and Main Street in Norman.

Upcoming construction projects identified as part of the corridor study include: intersection modification on Robinson Street just west of I-35 in Norman (contract awarded); modifications to the I-35 service roads and ramps at Indian Hills Road in Norman; and modifications to the I-35 service roads and ramps at South 19th Street in Moore.

I-35 – UPCOMING

I-35 PAVEMENT REHABILITATION BETWEEN I-44 AND KILPATRICK TURNPIKE

An estimated $8 million for pavement rehabilitation in FFY 2021.

I-35 AND I-240 CROSSROADS INTERCHANGE

Four remaining construction phases scheduled for FFY 2021, 2023, 2025 and 2027 will complete reconstruction of the I-35 and I-240 junction to a multi-level interchange with flyover ramps, similar to what is being built at I-235 and I-44.

The estimated costs for the phases are $28 million, $21 million, $20 million, and $30 million.

I-44

I-44 PAVEMENT AND BRIDGE REHABILITATION BETWEEN I-40 AND SW 74TH ST.

This $28 million project will rehabilitate the I-44 bridges and pavement between I-40 and Southwest 74th Street continues through 2021.

The project includes the rehabilitation of the bridges over the Oklahoma River, bridges over Southwest 29th Street, the eastbound bridge over Independence Avenue, bridges over Southwest 59th Street and the eastbound bridge over I-240.

This article originally appeared in the March 2021 edition of The Point.